VIDEO1
272KB |

VIDEO2
258KB |

VIDEO3
97KB |

VIDEO4
121KB |

VIDEO5
138KB |

VIDEO6
140KB |

VIDEO7
140KB |
| The
reconstruction experiment: splitting the log |
Conservation:
removing the pieces from the freeze-drying chamber |
Conservation:
placing the pieces in the freeze-drying chamber |
Conservation:
removing the pieces from the freeze-drying chamber |
The
reconstruction experiment:
twisting yew withies |
The
reconstruction experiment: waterproofing the central seam with
moss |
The
reconstruction experiment: waterproofing the central seam with
moss |
| |
|
|
|
|
|
|
The Dover Bronze Age Boat
In September
1992, the superbly preserved remains of a Bronze Age stitched plank
boat were discovered buried 6m below the streets of modern Dover.
The long process of analysis, conservation and re-assembly will
be completed in 1999. A few short notes on the project thus far
are presented below.
Discovery
and Excavation
In
September 1992 the Dover A20 project was drawing to a close.
For well over a year, archaeologists from the Canterbury Archaeological
Trust had been monitoring roadworks linking the port of Dover
with the new channel tunnel and motorway links with London.
Ironically, the first land link with the continent for 8,000
years was to indirectly bring to light the earliest example
of sea transport yet found. |
|
|
| |
|
|
 |
|
The
discoveries of the A20 project were abundant and important,
though their full potential has not yet been realised. A deep
shaft excavated for a pumping station, some 200m inland, was
proving to be the climax of this long-running project. A section
of the medieval town wall, its stones rounded by the battering
of the sea, overlay the massive squared timbers of a Roman
harbour mole. The recording and recovery of these timbers
was seen as our last important discovery, and we prepared
to wind down the project.
The shaft
was excavated still deeper, however, and routine monitoring
continued. The Field Director, Keith Parfitt, noticed some
fragments of timber disturbed by the contractor's machine
bucket lying in sediments underlying the Roman harbour timbers.
After closer examination, he realised that he had found part
of a prehistoric boat. It was midday, Monday 28th September;
Keith managed to negotiate a temporary halt to the contractor's
work schedule. Telephones began to ring. |
| |
|
|
By
11.30 the next morning, a team of specialists was assembled
on site, including experts from English Heritage, who had
immediately made funds available to recover this unexpected
find. We were initially given 3 days to excavate the boat,
later extended to six days. We worked from first light until
late into the night, with water gushing into the cramped cofferdam,
only 6m long and 5m broad. After recording, the boat was cut
into sections and lifted by crane on Saturday 3rd October,
to be stored in a temporary water tank provided by Dover Harbour
Board. The last fragment, running into the section, was recovered
in about 20 minutes on Sunday 4th.
We had
recovered the mid-section of a prehistoric boat, probably
of Bronze Age date judging by the technological parallels
with the Ferriby river boats, recovered half a century before.
It was a discovery of European, if not world-wide importance.
The decision was made to sink another shaft, slightly larger
at 7m long and 5m broad, immediately adjacent to the original
discovery. After a week to recover, on Monday 12th October,
we were back down another hole, now with a slightly better
idea of what to expect! Miraculously, the second shaft straddled
one end of the boat, crucial to our understanding of the form
and function of the original vessel. This time we had nine
days grace. We cut the boat into sections and lifted on Monday
19th October, leaving Tuesday to complete palaeoenvironmental
sampling.
The other
end of the boat lay near to standing buildings, and given
the potential costs and the possibility it had been destroyed
by the later Roman timber construction, it was decided not
to attempt to recover this end.
back to top |
| |
|
|
Analysis
We have
a 9.5m length of a perfectly preserved Bronze Age boat, about
2.3m wide and dated by 14C to about 1,600 BC. The section
recovered consists of four main planks of oak. Two flat planks
form the bottom, each carved out of half logs, leaving upstanding
cleats and rails allowing its jointing with other boat timbers.
These bottom planks were joined together along a central butt
joint, with transverse timbers and wedges hammered through
the cleats and central rails. Curved side planks were stitched
to the bottom of the boat with twisted yew withies. These
side planks also possess side cleats carved out of the solid
wood. The timbers forming the end of the boat splay into a
Y-shape, intricately carved from the main planks. This originally
would have held a carved wooden board, reminiscent of a modern
"punt". There was clear evidence for the presence and some
dimensions of this missing end board; there was also evidence
for at least two other main structural timbers. On the top
of the curved side planks (or "iles") was another row of stitches,
cut through in antiquity. There were clearly two further side
planks, and the boat had been deliberately dismantled (albeit
partially) when it was abandoned. She had been made waterproof
by pressing in a "stopping" (possibly animal fat) into the
stitch-holes and along the seams, where the stopping was overlain
by pads of moss wadding, compressed and held in place by long
thin laths of oak under the yew stitches. The boat had clearly
been used extensively. Tool marks on its bottom (outboard)
surface were differentially worn away, suggesting it had been
beached regularly on a sand or gravel shore. The main timbers
had split and were repaired by stitching wooden laths over
the damage. |
|


|
| |
|
|
The
boat was made from at least 3 straight-grained oak trees,
well over 300 years old when felled, grown in dense woodland
with few side branches. The original logs were probably 12m
long and 1.1m in diameter, weighing about 12 tonnes each.
Analysis of the tree rings shows that the two bottom planks
(each carved out of half a log) were from two different trees,
probably "wolf trees", out-competing their neighbours in early
growth to grow fast above the forest canopy. Such trees are
extinct in Western Europe today. The withies, unusually made
of yew, a tough durable material rather difficult to work
with, were about 1.4-1.8m long and between 6-16 years old.
They probably derived from a coppiced stand of fastigated
yew, now extinct in England.
The boat
timbers displayed well-preserved toolmarks, though there were
no clear examples of recurring tool signatures. There was
particularly good survival on the bottom of the boat, suggesting
the boat was less than 10 years old when abandoned, though
they may have been protected by matting or dunnage of some
kind. A minimum of five tool types could be deduced from the
toolmarks, including adzes, axes, chisels and gouges. |
| |
|
|
An
experimental reconstruction of a 3m section of the boat in
August 1996 allowed us to better understand the sequence of
construction of the boat. Study of the rays and rings of the
original timbers revealed in the cross-sections through the
boat showed that they had been substantially compressed during
its long burial, by as much as 50% in some instances. The
reconstruction took this compression into account, helping
us to visualise the appearance of the original vessel. Using
facsimiles of local contemporary tools, we found that the
toolmarks created by modern woodworkers matched almost exactly
those on the original boat. Indeed, the inexperienced woodworkers
easily achieved a finer finish on the reconstruction than
on the original. Whilst there can be no questioning the expertise
of the Bronze Age woodworkers, this does seem to imply that
they were not seeking a fine finish to the timbers. Perhaps
they were more interested in function than display?
The
original boat
Study
of the hull has led us to believe that we have recovered the
majority of the boat. It probably had a vertical transom end,
making the Y-shaped end the bow of the vessel. A minimum reconstruction
suggests the boat was about 11.7m long, with a beam of 2.26m
and a height from her bottom of 0.8m. She probably weighed
around 2.3 tonnes. |
|


|
| |
|
|
Various
permutations of crew and cargo have been studied using this
proposed hull form. With a crew of some 16 paddlers (together
with four bailers!) The boat could easily achieve 5 knots
and made way in winds of Force 4 with waves up to a metre
high. Even adding 3 tonnes of cargo, reducing freeboard to
about 0.45m, the boat could still have travelled in Force
3 winds with waves 0.6m high. Five knots appear to have been
the maximum speed for maintained paddling; even a small crew
of four paddlers (and one bailer) could have propelled her
at up to 4 knots. Above five knots, however, the drag created
by the hull form rises steeply, so that even a speed of 5.5
knots would have been impossible to maintain.
The boat
appears to have been suitable for carrying a significant cargo
at a reasonable speed, in fairly rough weather, possible over
long distances. On a good day, with favourable tides, she
could perhaps have covered 30 nautical miles with continuous
paddling.
Analysis
of the soil samples taken during excavation suggests the boat
was abandoned in a completely freshwater environment, probably
a shallow braided river channel some distance from the sea.
The valley floor was probably cleared, perhaps with some settlement
nearby; the deposits immediately surrounding the boat contained
charred cereal grain and other domestic refuse. The absence
of oak pollen may suggest the boat was not built in the Dour
valley.
The
evidence suggests that the Dour valley was not suitable
for a boat of this size, unlike the broad estuaries of the
Severn and Humber. It seems clear that the boat travelled
by sea; Dover is flanked by steep cliffs denying an easy
coastal passage. A thin layer of marine sand on the bottom
of the boat, containing glauconite not found in the Dover
area, may have been trodden in by Bronze Age mariners on
some distant beach. Although no cargo was found, a small
piece of unworked shale on the bottom of the boat proved
on analysis to originate from Kimmeridge Bay, some 160 miles
to the west.
back to
top
Conservation
& Re-assembly
The
boat was cut into 32 pieces during excavation. English Heritage
conservators proposed that these were to be soaked in a
solution of Polyethylene Glycol (PEG) for about a year,
after which they would be freeze-dried. The Mary Rose Trust
in Portsmouth carried out the freeze-drying. The conservation
process was a great success, with minimal overall shrinkage
or distortion of the pieces (though the little that did
occur was not uniform and has presented problems in the
boat re-assembly). The pieces returned to Dover in August
1998.
Five
years on, therefore, we were faced with the task of re-assembling
these pieces to regain the original form of the boat. This
was not to prove a straightforward assignment.
First,
the boat pieces, whilst heavy, were also rather fragile
and brittle. Though there had been only minor shrinkage
or distortion of the pieces during conservation, what little
there was had affected their relative shapes; this was particularly
true in regard to the curvature of the ile planks. The pieces
thus represented the parts of a complex three-dimensional
jigsaw, some of which had warped slightly in relation to
each other. In addition, the boat had opened up and become
deformed after its long burial; this shape was reflected
in that of the boat timbers. To make the pieces fit, we
had to realise the exact shape of the boat as found, rather
than the original form of the hull. Crucially, no one knew
the exact form of the outboard surface of the boat; this
would only be seen after we had re-assembled the pieces.
A plan
for this process was drawn up and approved prior to the
return of the boat pieces to Dover; however, all concerned
recognised that there would be a certain amount of experimentation
and variation of our original plans. Quite how much trial
and error lay before us was not fully appreciated at the
time.
In essence,
the plan was to support the boat on a custom built cradle.
The pieces were not to be glued or pegged together, but
individually supported in their correct positions. The cradle
was designed to be adjustable so that it could take up the
shape of the outboard face of the boat as it was put back
together. A set of adjustable tables was commissioned, which
allowed the boat pieces to be offered up to the cradle and
propped in their correct position relative to each other.
They could be used single or bolted together to accommodate
the larger boat pieces. They were mounted on castors to
lessen the amount of manhandling of the timbers, and also
allow them to be moved easily away from the cradle to allow
its adjustment.
The
whole procedure needed to be undertaken in a controlled
environment. It proved impossible to maintain the correct
conditions in the gallery as a whole, so a temporary 'room
within a room' was erected, allowing work to be carried
out at the appropriate temperature and humidity. The re-assembly
team comprised Peter Clark, Barry Corke and Adrian Murphy
of the Canterbury Archaeological Trust. Specialist engineering
support was provided by Dr Edwin Gifford, and final conservation
treatment of the boat was carried out by Sue Bickerton and
Mark Jones of the Mary Rose Trust.
Re-assembly
The
main re-assembly project could now begin. The sections of
boat were stored in the temporary workspace, stacked on
shelving around the boat cradle.
The
bottom planks
The
first pieces to undergo assembly were the main base planks
from the second cofferdam. These pieces were in a better
condition than some of the others and it was felt that they
would enable the team to get a feel for the boat and its
requirements before tackling some of the more fragmentary
pieces. The planks were supported on three tables, all bolted
together, which were wheeled towards the cradle with the
beds high enough to clear the ribs.
Using
the 1:1 drawn profiles and plans from the study phase, adjustments
to the levels and attitude of the pieces were made until
the correct position was attained.
|
| |
|
|
The ile planks
The ile
planks were to prove even more difficult. Not only did the
iles have to match with the adjacent ile timbers, the small
section of base plank, attached by the stitches on each one,
had to align with the relative cut of the base plank already
on the cradle. In addition, the ile had to sit at the correct
angle, or as close as possible, to keep the strake line consistent.
It was decided that the complete side should be offered up
at the same time so that each piece could be directly related
in situ. |
|
 |
| |
|
|
 |
|
Once
the probable best alignment had been achieved, the final support
strategy could be considered. The original theory was to bolt
the secondary rib sections onto the primary ribs, to form a
single element with one joint. An 18mm plywood ile support was
cut to the correct shape and temporarily clamped to the base
plank rib. It became clear that we had significantly underestimated
the degree of variation of the outboard surface of the boat.
The rib plates, intended to allow fairly minor adjustments,
were in places bent 100mm or more above their supporting ribs.
The intended secondary rib sections would have to be extremely
broad and bulky to make the transformation from the horizontal,
primary rib section up and around the ile. |
| |
|
|
| Fitting
the trimmers also proved troublesome, as the bolting flange
was not long enough to cover this variance. After reviewing
the situation with the ile pieces in situ, the decision was
made to abandon the idea of the two-section rib and make a set
of single piece ribs, individually tailored to the appropriate
outboard contour of the hull. |
| |
Supporting
the southern end
Time soon
became increasingly short; the re-assembly process was but
one part of the programme to establish the gallery, whose
opening ceremony had already been organised. The complex southern
end section had still not been put into place. The final mechanism
for supporting the piece was a subject of much discussion.
Ultimately a one-piece welded support bolted to the existing
spine plates seemed to be the most suitable answer. Struts
extending back to the first available rib would help to offset
the weight distribution. A wooden mock-up was prepared to
form the template for this complex support. |
|
 |
| |
|
|
As
the newly-made pieces were returned, each rib was bolted into
position with relatively few problems and trimmers added.
All of the temporary wooden formers and legs were gradually
removed to leave the boat supported solely on the cradle.
The end of the spine had to be cut off as the design had changed.
A cap, made of the same material, was fitted to conceal the
alteration and the new end section was bolted into place.
The re-assembly of the main boat pieces was complete.
back to top |
| |
|
|
Lowering
the boat
It now
remained to lower the boat to its display level. The height
of cradle suitable for the re-assembly process was clearly
unsuitable for presenting it to the public; many people, particularly
children, would be unable to see the inboard surfaces of the
boat. The entire re-assembled boat needed to be lowered by
0.5m This was an intensively nerve-wracking procedure; the
re-assembly team had spent ten months positioning the boat
pieces and customising the cradle support. Any mistake, even
if the timbers themselves escaped damage, would require the
procedure to be gone through again. |
|
 |
| |
|
|
The
method adopted was essentially quite simple. Four steel girders
were manufactured with a bracket welded on their upper surface
that allowed them to be bolted to the cradle spine adjacent
to the main support columns. These were supported on stacks
of timber. Simple scissor jacks were bolted to either end
of each girder, which were then set atop further stacks of
smaller timber blocks. When all was in place, the cradle spine
was unbolted from its supportive columns.
It was
essential that the boat was lowered very slowly, being kept
absolutely level at all times. A trial run was carried out
prior to the re-assembly to evaluate the method, the cradle
weighed down with steel plates and scaffold boards to simulate
the weight of the boat. This proved highly successful, and
many useful lessons were learnt. It was a very different exercise
lowering the boat itself. A team of eight volunteers was assembled,
each charged with manning one of the jacks. The cradle was
plastered with spirit levels along the spine and on the transverse
ribs so that any change in angle of the boat cradle could
be monitored as it was lowered. (During the trial run, teacups
were filled with water and placed atop paper napkins in saucers
at various points along the cradle. Any jolting or tipping
would result in water spilling and dampening the napkins.
They stayed dry).
On a chant
from the project manager (Peter Clark), each of the volunteers
raised the jacks one turn (clockwise). The boat was now freed
from its supportive columns, resting only on the eight jacks
atop their stacks of timber. The re-assembly team now replaced
the supportive columns with new ones, only 0.5m high. They
then unscrewed and removed the topmost timber block from the
main stacks. Then, again following a chant, the jacks were
lowered, one turn at a time (anticlockwise) until the steel
girders rested on top of the next main timber block. The jacks
were slackened off, a timber block removed from each of the
small timber stacks, and the strain taken up once more. This
process was repeated until the main spine rested on the new,
shorter supportive columns.
Finally,
the boat reached its final position. The cradle spine was
bolted to the new supportive columns, and the steel girders,
wooden blocks and jacks removed. It is difficult to describe
the feeling of relief felt by the re-assembly team as we stood
back from the display case; in spite of all our fears, everything
had gone well. The entire process only took 70 minutes to
carry out.
Completing
the case
We could
then address the final stages of re-assembly; fitting small
pieces of timber, such as sections of laths, wedges and transverse
timbers, and reconstituting stitches that had become separated
from the boat pieces. We tried very hard to bring the boat
back to the condition in which it was found. After a final
surface treatment of the re-assembled timbers, the job was
complete. |
| |
|
|
The
contractors glazed the case with a series of toughened glass
panels, 19mm thick and sealed with clear mastic. This allowed
a check of the environmental control system to be undertaken,
after which the case was sealed behind a protective timber
hoarding as the rest of the gallery was fitted out.
The Dover
boat has now reached a safe haven after her long journey down
the millennia. She must surely enter her fifth millennium
as one of Europe's greatest prehistoric discoveries. |
|
 |
| |
|
|
| |
|
|
|
| |
|
|
| |
|
|
Acknowledgements
As might
be imagined, the boat owes a debt to a great number of individuals
and organisations. Particular note should be made here to
the staff of English Heritage, Dover Museum, the Canterbury
Archaeological Trust, P & O Ferries, Dover Harbour Board,
the Heritage Lottery Fund and the members of the Dover Bronze
Age Boat Trust.
Peter
Clark, Project Director
Canterbury Archaeological Trust
92a Broad Street Canterbury Kent CT1 2LU UK
e mail: pete.clark@canterburytrust.co.uk
|
|
 |
| |
|
|
VIDEO8
110KB |

VIDEO9
120KB |

VIDEO10
112KB |

VIDEO11
80KB |

VIDEO12
76KB |

VIDEO13
76KB |
| The
reconstruction experiment: cutting wedge holes and stitch holes |
The
reconstruction experiment:
felling the tree
(Bronze Age Style) |
The
reconstruction experiment:
felling the tree
(20th CenturyStyle) |
The
reconstruction experiment:
splitting the log |
The
reconstruction experiment:
splitting the log |
The
reconstruction experiment:
splitting the log |
| |
|
|
|
|
|
More information in Canterbury's
Archaeology 20002001, Post
Excavation and Research PDF
Back to Top


Back to Top |